The estimated cost of planned repairs at Renfrew Victory Baths has risen from £600,000 to £910,000. That figure excludes repairs to the roof above the pool, which Storm Boelo damaged after the plans were drawn up.

The council does not yet know how much the roof repairs will cost.

Renfrewshire Council’s Finance, Resources and Customer Services Policy Board authorised officers to award the contract for the planned repairs to Clark Contracts Limited on Thursday, 19th November 2026. The award is subject to approval of the additional funding and an assessment of the storm damage.

The planned work includes concrete repairs and refurbishment inside and outside the building. The contract gives a start date of 18th January 2027 and a finish date of 30th April 2027. Officers said they would know more about the impact on that timetable once the roof had been assessed.

Clark Contracts quoted £672,457.07 excluding VAT for the planned repairs. The tender price alone exceeded the original £600,000 estimate. With a 15% allowance for unforeseen work, the board authorised a contract value of £773,325.63 excluding VAT. The wider £910,000 project estimate also allows for professional fees.

Officers sought a further £310,000 for the planned work. In June 2025, the board had agreed to provide up to £500,000 from the Renfrew Common Good Fund and £100,000 from the council’s Financial Sustainability Fund.

Councillor Alison Ann-Dowling asked how soon the roof could be assessed, how much of the repair cost insurance would cover and whether the council would seek outside funding.

She asked: “What is the long-term plan for the operation, maintenance and funding of Victory Baths once those repairs are complete?”

Alastair MacArthur, the council’s director of finance and resources, said the damaged section of roof was particularly difficult to reach. He told councillors he understood the assessment would take place in the coming days.

Mr MacArthur said the council was working with OneRen, which holds the insurance policy for the baths. He said: “Some of the costs that we are anticipating are related to weather damage, which should be covered by insurance arrangements.”

Councillor Graeme Clark asked what the council could learn from the increase in costs, drawing a comparison with its work on Paisley Museum.

Mr MacArthur said extra work could come to light on historic buildings even after initial surveys. He said: “That is often tied into the fact that you simply do not know the extent of the works that are required until you are out on site and pulling things apart.”

The Category B listed baths date from 1921. Designed by Paisley architect Thomas Graham Abercrombie, the 25-yard pool retains its viewing gallery and the original layout of the poolside cubicles.

A further report will go to the board once the council knows more about the cost of repairing the roof.

By Ricky Kelly

Main writer for Renfrewshire News

Leave a Reply

Your email address will not be published. Required fields are marked *